Papendrecht Bridge Lift
Sarens lifted and removed the 950t movable deck section of the Papendrechtsebrug as part of a nine month renovation for Hollandia Infra. The firm used a combined lifting and tensioning system to manage an offset centre of gravity and keep the structure stable.
Early in August 2026 Sarens removed the movable deck section, the Brugklep, of the Papendrechtsebrug in Papendrecht, the Netherlands. The work forms part of a major renovation for customer Hollandia Infra, and follows a road closure of the N3 from 17 July 2026 until 21 April 2027 to replace the bridge leaf and operating systems.
The bridge section weighed about 950 tonnes and had a centre of gravity that sat beyond the supporting barge. Because of that offset, Sarens designed a combined lifting and tensioning solution to control and stabilise the complete arrangement throughout the lift.
The engineered system used four CS1000 climbing units for the jacking lift and two 200 tonne strand jacks to apply tension and control the forces caused by the offset centre of gravity. The deck was jacked roughly 6 metres to allow the counterweight to be released from the bridge basement.
Sarens also built a purpose designed guiding frame to control the structure during both the lift and the lowering. The company says the guiding frame was crucial in maintaining the stability of the integrated arrangement, which combined lifting, tensioning, guiding, ballasting and transport systems.
Preparation was extensive because the execution window required continuous work in shifts over three consecutive days. Specialists were brought in from across Europe, with the project team peaking at 20 personnel.
Marine planning was also critical. The operation took place on one of the busiest river sections in the Netherlands, so the river was closed to shipping for 24 hours. Two barges were on site for four days while the works were carried out.
Sarens will support the later installation of the movable deck as part of the next phase of the renovation. The overall project is due for completion on 21 April 2027.



torque.newsroom
Seen something on the road? Send the newsroom a tip.
Related news
Boreas Mobilisation Complete
Volvo FH for Mortimers
Buy the photographs
66,000 images and counting, ready to download.
Subscribe