Sarens is handling module transport, installation and heavy lifts on Saudi Aramco’s Fadhili Gas Increment Program. The operation has moved 63 modules and used high-capacity cranes and SPMTs to place a 1.030 tonne unit.

By the torque.news newsroom 23 November 2026 2 min read
Sarens lifts Fadhili work
Sarens lifts Fadhili work

Sarens is executing the full scope of module transport, installation and heavy lifting on the Fadhili Gas Increment Program, a major gas infrastructure expansion led by Saudi Aramco near Jubail.

The project includes new gas processing facilities and upgrades to existing operations. It aims to raise production capacity, improve energy efficiency and support long term regional growth and job creation.

Sarens won the work on the basis of its track record with the client, a competitive offer and previous experience on complex Aramco projects. The company also provided dedicated coordination and native language support to meet the client’s requirements.

A total of 63 modules were moved from the fabrication yard to site. Transports covered distances of up to 5 kilometres and used self propelled modular transporters, SPMTs. Several modules were positioned using a mix of crane lifting and SPMT operations.

The heaviest module reached 1.030 tonnes. Some units measured up to 42 metres long and almost 29 metres high. Elevated centres of gravity from installed components added complexity to transport and final positioning.

Sarens deployed a broad crane fleet. Key crawler units included the LR11350, CC2800-1, CC2500-1 and CC2400-1, supported by LR1300 and LR1250 machines and a range of auxiliary cranes. The LR11350, fitted with a 78 metre main boom, handled critical lifts including a 520 tonne boiler module. The CC2800-1 was used for both module installation and flare stack lifts.

Transport stability relied on 72 axle lines of SPMTs. The company also brought in specialised rigging equipment sourced from several international locations, and mobilised the LR11350 from Egypt.

Planning and coordination were intensive. Early stages featured many simultaneous activities, which required increased manpower and equipment mobilisation. At peak there were up to 75 personnel working across greenfield and brownfield areas, where restricted access, ongoing operations and limited space added further challenges.

Environmental factors also affected the programme. Strong winds and frequent sandstorms needed continuous monitoring and occasional changes to lifting schedules to maintain safety.

Despite those constraints, Sarens reports steady progress, supported by maintained equipment and close cooperation between engineering, logistics and site teams. The firm continues to carry out high precision lifting and transport work as the project moves towards completion, supporting the development of essential energy infrastructure in the region.

Filed under Operators

torque.newsroom

Seen something on the road? Send the newsroom a tip.

AdvertisementKraker Trailers

Related news

Buy the photographs

66,000 images and counting, ready to download.

Browse the gallery