Norwegian haulier CN Heavy Transport has put a new SCHEUERLE STB 260 side girder bridge into service on two demanding transformer moves from Bogen to Bjørnfjell. The 386 tonne combination climbed to about 500 metres and squeezed through tunnels with just 5 centimetres clearance.

By the torque.news newsroom 18 November 2026 2 min read
SCHEUERLE STB 260
SCHEUERLE STB 260

Norwegian heavy haulage specialist CN Heavy Transport AS has put a new SCHEUERLE STB 260 side girder bridge straight into operational use. The unit carried two power transformers, weighing 128 and 185 tonnes, on roughly 70 kilometres of northern Norwegian roads to Bjørnfjell on the Swedish border.

The heavier transformer measured about 9 metres long, 3.2 metres wide and 4.65 metres high. Together with the STB 260, trailer units and prime movers, the complete transport combination reached a gross vehicle weight of 386 tonnes and an overall length of 71.5 metres.

Tough route, tight clearances

The route ran from the port of Bogen and used sections of the E10 and E6. The convoy climbed from sea level to an altitude of around 500 metres, faced gradients up to 10 per cent, negotiated tight roundabouts and passed through several tunnels. One of the biggest challenges was the Leirvik Tunnel, where the combination had just 5 centimetres of clearance to the roof at its narrowest point.

Ole Kristian Ruud, project manager at CN Heavy Transport AS, said the STB 260 expanded the company’s heavy haulage capabilities and opened up new opportunities for transformer and infrastructure transports. He added that the bridge proved itself on the climb and on the tight manoeuvres required by the route.

Design and compatibility

The STB 260 has a deadweight of around 40 tonnes and a rated payload of up to 260 tonnes, giving a very favourable payload-to-deadweight ratio. SCHEUERLE also carried out overload testing beyond the rated capacity before delivery.

For the Norwegian moves CN Heavy used a 2 by 12 axle-line configuration to carry loads up to 185 tonnes. The STB 260 can be combined with SCHEUERLE K25 modular platform trailers, and as CN Heavy demonstrated, with existing NICOLAS modular platform trailers too. The bridge offers a lifting range of 1,500 millimetres, various girder configurations for different load heights and an integrated roll stabilisation system.

The two transports marked the STB 260’s operational debut in CN Heavy’s fleet and the first privately operated side girder bridge in Scandinavia. The transformers will support regional energy infrastructure, including the railway link between Narvik and Kiruna and cross-border power transmission.

Filed under Operators

torque.newsroom

Seen something on the road? Send the newsroom a tip.

AdvertisementKraker Trailers

Related news

Buy the photographs

66,000 images and counting, ready to download.

Browse the gallery